Team 15 - Enneapous
Meeting Minutes - Jan. 15, 2010
In attendance:
Nathan, Danielle
Tasks:
- Nathan - Work on setting up the simulation so we can start delegating chunks of code.
Notes:
- Speed controller local path planner still need to be implemented.
- Global path planner and occupancy grid just need to be updated to a 3-D environment.
- Algorithm needs to be simplified from the research paper can be coded by Danielle or Mike.
- Computer can’t run the software remotely, testing needs to occur at the school.
- Should we be meeting the computer lab once a week?
- We’re estimating the total project will take 10-20 full days of work.
- Wednesday at 2:00pm is our new meeting time.